216DB61 The first set of 9H gas turbine iDCS project of Guoneng Zhishen was successfully put into operation

At 13:58 on October 26, Unit 1 of the Phase II backbone support Peaking power supply (Class 9H gas turbine) project of Guangzhou Pearl River LNG Power Plant successfully passed 168 hours of full load trial operation, marking the successful application of National Energy Zhizhen autonomous controllable intelligent decentralized control system (iDCS) in the field of gas turbine generation.
Dec 25th,2023 167 Views
At 13:58 on October 26, Unit 1 of the Phase II backbone support Peaking power supply (Class 9H gas turbine) project of Guangzhou Pearl River LNG Power Plant successfully passed 168 hours of full load trial operation, marking the successful application of National Energy Zhizhen autonomous controllable intelligent decentralized control system (iDCS) in the field of gas turbine generation.
The Zhujiang Phase II gas turbine project is a key construction project in Guangdong Province and the first EPC general contract project for H-class gas turbine power generation in China. Under guaranteed performance conditions, the combined cycle efficiency can reach 63.7%, which is the highest level for the 600MW combined cycle generator units already built or under construction in China. Based on the accumulated experience in the field of thermal power generation, combined with the actual requirements of iDCS intelligent function of this project, Guoneng Zhishen uses fieldbus and intelligent control technology to deeply integrate data analysis, artificial intelligence, advanced control and other technologies with traditional gas turbine power generation industry technologies. The development and deployment of APS (one-click start and stop), intelligent analysis,

intelligent monitoring panel, intelligent alarm, intelligent operation, intelligent control and other functional modules, to achieve real-time information integration in the power generation process and intelligent control of the "large closed loop", fully ensure the operation safety and performance optimization of the unit.
The successful commissioning of Unit 1 of Guangzhou Zhujiang Phase II Gas Turbine Project fully proves the product, technology and service capabilities of Guoneng Zhishen in the field of gas turbine power generation, and provides important guiding significance and demonstration role for the later gas turbine projects such as Huizhou, Zhaoqing and Shijiao. In the future,

 Guoneng Zhishen will continue to uphold the enterprise spirit of "hard work, dedication, innovation and striving for the lead" of the group company, actively practice the mission of the central enterprise, and make new contributions to the follow-up construction of iDCS of Zhujiang Unit 2.